The plans and specifications for the project have been approved.
The project was advertised for contract in November 2016.
Bids were received on December 28, 2016.
Contract was awarded in January 2017.
Work is scheduled to start April 3, 2017.
Work duration after start about 20 days.
Road will be slightly reconfigured during the repaving—11 feet travel lanes and 6 feet paved shoulder (that is a one foot wider shoulder on each side and one foot narrower travel lane in each direction.
Updated 03/20/17